Well at long last we are now able to remove the unsightly tennis courts at SMH and replace it with an extension to the main pitch. This will be an all-grass facility. We did look into the possibility of funding for 3G but the FA advised against us as the return on a very large investment would not fit the requirements of the Football Foundation model.
The result will give us two 5v5 pitches , one 7v7 pitch and one 9v9 pitch (In lieu of the 7v7 and a 5v5)
The funding has been provided through RVBC Communities grant funding and RVBC Shared prosperity fund, which is a central government fund.
We must say a big thank you to Phil Hartley for his work in securing the funding through a lengthy and involved application process!!
The work is scheduled to start early December 2024, which will see approximately 400 tonnes of ground removed and 500 tonnes of topsoil brought in. This will be allowed to settle over winter.
The drainage system will be installed early March next year then graded and seeded. The drainage system will feed into the existing system in the main 7v7 existing pitch.
Our intention is to have the surface ready to use at the start of next season.
We are not anticipating any disruption to the current use of the facility during the rest of the season as all access will be via the adjacent farm.
We are of course very grateful to the farmer Mark Pearson for allowing the access.
Our contractors carrying out the work are Stuart O’Callaghan Ltd and Derek Craine, both recognised and respected local contractors.
This will see a much-needed extension to our great facility at SMH.